Hapcheon multipurpose dam was constructed on the narrow canyon of Hwang river, a tributary in Nakdong river. The dam located about 16 km north of hapcheon city is a concrete gravity dam with a total fill volume of 891 million ton. The dam of which basin area is 925งด has the dimensions of 96 meters in height and 472 meters in length, and it creates a reservoir with the storage capacity of 790 million ton.

The dam commenced its construction in April 1982, and completed in May 1989. It has a 100MW hydropower plant which utilized its geographic characteristics by constructing a diversion tunnel to increase the rated head for the maximum hydropower generation.

In addition, a 29 meter high re-regulation dam with concrete and rockfill combined type was constructed at 5.6 km downstream from the main dam, and has a small scale flow-through hydropower plant.

The project supplies 599 ton of various water annually to the Busan metropolis and its vicinity, and it reduces flood damage by controlling flood inflows with the controlling storage of 80 million ton.

 

• Hydropower Plant

- Commercial operation :1st power plant : Mar. 15, 1989, 2nd power plant : Dec. 29, 1987
- Installed capacity : 101.2 MW (1st : 100MW, 2nd : 1.2MW)
- Annual average hydropower generation : 232 GWh